A company plans to make changes to change management processes for purchase orders.
Currently, the system requires an approval for any change. The company wants to implement re-approval only when there is a change to the quantity or the unit price in a purchase order.
You need to configure the change management process to require re-approval only on changes to quantity and unit price.
In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place: