How many calendar days can pass before the SLA fails?

You create a service level agreement (SLA) that will fail after seven days. You select a service calendar that uses 24-hour work days and no holidays. Saturday and Sunday are configured to be non-working days.
If no action is taken, how many calendar days can pass before the SLA fails?
A. 5 days
B. 7 days
C. 9 days
D. 11 days