You are a project manager for a Microsoft Dynamics implementation. The project is in the deployment phase, and you are planning the final data migration to production.
You need to split the effort into two phases: phase one and phase two.
How much time should you typically plan between phase one and phase two?
A. one day
B. one week
C. two weeks
D. one month