An architect proposes an HPE Moonshot 1500 chassis with m710p cartridges, an HPE Moonshot 45XGc Switch, and an HPE 4-QSFP+Uplink Module. The customer informs the architect that each cartridge requires a redundant 10GbE link.
How should the architect change the proposal?
A. Add another FlexibleLOM adapter for each cartridge.
B. Change the HPE Moonshot 45XGc Switch to an HPE Moonshot 180G switch.
C. Add another HPE Moonshot 45XGc Switch and 4-QSFP+Uplink Module.
D. Change the 4-QSFP+Uplink Module to a 16-SFP+ Uplink Module.
C