How should you answer?

Your company uses Project Professional 2013.
You are building a schedule by using predecessors to help determine a logical duration. The following image shows a baselined list of tasks with predecessors:


You have been told that Task C is optional, and you recommend inactivating the task to keep it visible on the schedule.
You need to determine what the results are to the schedule when inactivating Task C.
How should you answer?
A. The finish date is reduced by four working days, cost remains unchanged, and baseline cost is reduced by $400.
B. The finish date is reduced by five working days, cost remains unchanged, and baseline cost is unchanged.
C. The finish date is reduced by six working days, cost is reduced by $400, and baseline cost is reduced by $400.
D. The finish date is reduced by four calendar days, cost is reduced by $400, and baseline cost is reduced by $400.
E. The finish date is reduced by six calendar days, cost is reduced by $400, and baseline cost is unchanged.

microsoft-exams

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.