If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate? (Choose the best answer.)
A. The evolution of the cost spent on the project.
B. When all work will be completed to the Scrum Team can be released for other work.
C. When the work remaining will likely be completed if nothing changes on the Product Backlog or the Development Team.
D. When the project will be over if the Product Owner removes work that is equal in effort to any new work that is added.
C
B. When all work will be completed to the Scrum Team can be released for other work.
This answer does not make sense. Should it read “completed ‘by’ the Scrum Team”?
Oops! Meant to say “completed, ‘so’ the Scrum Team can be released for other work”?
C