When you work on a change-management process, you generally identify potential change, review the change request, implement change, then reviewthe change and close the process. In which step should the stakeholder be involved?
A. Identifying potential change
B. Reviewing the change request
C. Implementation
D. Reviewing and closing
E. Depends on the stakeholder request