Multiple Scrum Teams working on the same project must have the same Sprint start date.

Multiple Scrum Teams working on the same project must have the same Sprint start date.
A. True
B. False

How To Pass PSM I Exam?

Scrum PSM I PDF dumps.

High quality PSM I PDF and software. VALID exam to help you pass.

How To Pass PSM II Exam?

Scrum PSM II PDF dumps.

High quality PSM II PDF and software. VALID exam to help you pass.

10 thoughts on “Multiple Scrum Teams working on the same project must have the same Sprint start date.

  1. The keyword here is MUST, remember that when MUST is used is because this is mandatory, so correct answer is B

  2. Correct Answer is A. As per scaled agile if multiple teams are working on same product they should have same cadence for sprint and PI planning so that their system demo is planned together on same day and MVP can go live when system demo for the work completed by all teams can be completed.

    4
    27
  3. I agree with Jimmy! According to Scrum.org, when working with multiple Scrum teams on the same project, it suggests Scaling Scrum with Nexus. In the Nexus Framework book, it says there is nothing to stop teams from observing their own Sprint cadence, as long as it is exactly divisible into the Nexus Sprint cadence.

    Therefore the answer should be “B”

  4. Answer B is correct because the new increment of a scrum team can be the input of another scrum team

  5. B is correct. Different scrum teams working on the same product may have different sprint cadence, and different start and end times.

    12

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.