What are two good ways for a Scrum Team to ensure security concerns are satisfied? (Choose the best two answers.)
A. Postpone the work until a specialist can perform a security audit and create a list of security-related Product Backlog items.
B. Add security concerns to the definition of "Done".
C. Add a Sprint to specifically resolve all security concerns.
D. Delegate the work to the concerned department.
E. Have the Scrum Team create Product Backlog items for each concern.
in E if they add “security” before concern, we will feel much better.
anyway agree with BE
Agree with BE
@Hamad, E, yes one of the two correct answers. The two correct answers ARE B and E.
Why? Because you deal with non functional requirements in two ways. 1) You add items to the product backlog which address them and 2) You add them to the definition of done.
So no problem with the proposed answers here.
It says scrum team. So it would be a collective effort facilitate by Scrum Master.
Why E is answer ??