What are two possible ways to achieve this goal?

Your team uses Microsoft Visual Studio Team Foundation Server (TFS) to manage your software projects. The operations team uses System Center Operations Manager (SCOM) and configures synchronization with TFS by using TFS Work Item Synchronization Management Pack.
You need to send information about production errors, including IntelliTrace information from System Center, to the software development team.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
A. Assign an existing Application Error from System Center to the development team by using the TFS connector and opening an error alert. Select the Assign to Engineering option from the Alert Status menu.
B. From System Center, select an existing alert, and enable full IntelliTrace collection by using the tasks panel. Once the IntelliTrace file is associated to the alert select the Assign to Engineering option from the Alert Status menu.
C. From the TFS Administration Console, select the Import IntelliTrace files menu, and associate the IntelliTrace file to a new work item.
D. From System Center, select an existing alert, and enable the full IntelliTrace collection by using the tasks panel. Once the IntelliTrace file is associated to the alert, create a new work item in TFS, and add a link to the new System Center alert.