What are two possible ways to achieve this goal?

You are a program manager for a company that uses Project Server 2013 and Project Professional 2013. You manage the implementation of a data warehouse. You have set up your program master project with subprojects for each implementation area. You need to make edits to the dependencies between projects. What are two possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose two.)
A. View the subproject in Project Web App (PWA) and choose Edit. Then add your dependencies in the predecessor’s/successor’s column.
B. Open the program-level project from Project Web App (PWA) by using Project Professional 2013. Highlight the tasks you wish to link for a dependency with the control key. Then click the link button on the tool bar.
C. Open the program-level project and the subproject from the Project Web App (PWA) and save them to your local machine. Then add your predecessor’s/successor’s column in either file.
D. Open each of the required subprojects from the Project Web App (PWA) by using Project Professional 2013 and create the link in the predecessor’s/successor’s column to the other projects using the <>Project NameTask ID.
E. View the program-level project in Project Web App (PWA) and choose Edit. Then add your dependencies in the predecessor’s/ successor’s column using the <>Project NameTask ID.