What is the correct setup to accomplish this?

Exhibit 1.


Exhibit 2


A network administrator wants to create a backup IP route to 10.1.20.0/24 on Switch-1. The backup route should use Link 2, and it should only be used if Link 1 is down. What is the correct setup to accomplish this?
A. an IP route through 10.0.2.2 with administrative distance 1
B. an IP route through 10.1.20.1 with administrative distance 1
C. an IP route through 10.0.2.2 with administrative distance 10
D. an IP route through 10.1.20.1 with administrative distance 10

Download Printable PDF. VALID exam to help you PASS.