What is the next step when you use the Microsoft Dynamics Sure Step Methodology resource management techniques?

You are a project manager. You create a work breakdown structure (WBS).
What is the next step when you use the Microsoft Dynamics Sure Step Methodology resource management techniques?
A. Plan material resources that will be needed.
B. Plan and use the plan-do-check-act cycle.
C. Plan and collect the project requirements.
D. Plan and schedule stakeholder project reviews.