What must be taken into account when developing a technical action plan?

The storage integrator is about to add new HPE 3PAR StoreServ 8200 to a customer’s existing SAN infrastructure.
What must be taken into account when developing a technical action plan?
A. customer change control procedures
B. action plan audience
C. environmental requirements
D. level of support

Download Printable PDF. VALID exam to help you PASS.

One thought on “What must be taken into account when developing a technical action plan?

  1. A,

    Customer change control procedures might affect a procedure to implement and test the storage solution. Such procedures can prevent a new solution from negatively affecting operations and must be taken into account when developing a technical action plan.