What should the integrator recommend to the customer for the installation of the racks?

A customer is implementing a new rack solution in their datacenter. The racks will be supporting a variety of HP ProLiant Gen9 servers in each rack, and the racks will be sharing a common hot aisle due to space limitations. The customer is concerned about the amount of heat that will be generated.
What should the integrator recommend to the customer for the installation of the racks?
A. Verify that the ProLiant Gen9 servers have redundant fans installed in them.
B. Verify that the backs of the racks are a minimum of 48 inches (121.9 cm) apart to allow for heat release.
C. Verity that there are enough cooling vent tiles in the shared hot aisle.
D. Verify that the rear rack doors are solid in order to deflect the heat up through the top of the rack.