What should you add to the task?

You manage a project by using Project Professional 2013.
The Indicators column in the Gantt Chart view shows that there are overallocated resources for a task. A resource is assigned to multiple tasks at 100% on a specific day, totaling 2.5 hours of work for the day. The resource has availability of 8 hours for the day.
You need to solve this problem.
What should you add to the task?
A. A deadline
B. A Finish to Start relationship
C. A Finish to Finish relationship
D. More work