What should you do?

Your company is developing a web application by using the Microsoft Visual Studio Scrum 2.0 process template. The development team committed to deliver a set of Product Backlog Item (PBI) work items for the upcoming sprint.
You implement the initial tests for the PBIs in scope for the upcoming sprint. You plan to add more tests during the sprint.
You need to ensure that your test plan automatically includes any new tests.
What should you do?
A. · Create a Microsoft Excel spreadsheet that lists all the acceptance tests for the PBIs.
· Use a Pivot table to report the test cases per PBI.
B. · Create test case work items for the acceptance tests.
· Link these test cases to the PBI work items.
· Add a query based test suite that selects all test cases linked with the PBIs in scope.
C. · Create test case work items for the acceptance tests.
· Link these test cases to the associated PBI work items.
· Add the PBIs to the test plan.
D. · Create test case work items for the acceptance tests.
· Create a suite in Microsoft Test Manager (MTM) and add all test cases to this suite.