You manage a project for which the team has not delivered all of the story points committed to in a previous sprint.
You want to define the amount of work the team can commit to for the next sprint of the project.
What should you do?
A. Review the sprint burndown to define the amount of work.
B. Review the team velocity to define the amount of work
C. Allow the product owner to define the amount of work.
D. Review capacity of the team to define the amount of work.
Correct Answer: B
Explanation/Reference:
If your team has completed multiple sprints, you can forecast release and product completion dates and plan future projects more accurately by reviewing the velocity report. Based on the velocity of previous sprints that the report illustrates, you can accomplish the following goals:
* Track how much effort your team has reported as complete for each sprint.
* Estimate how much backlog effort your team can handle in future sprints if your team composition and sprint duration stay constant.
Reference: Visual Studio, Velocity (Scrum)