You are using the Microsoft Visual Studio Scrum process template. You recently finished a sprint.
You need to conduct a retrospective meeting prior to planning the next sprint.
What should you do?
A. Analyze items in the product backlog for the next sprint.
B. Analyze the previous sprint to identify what the team is going to do differently during the next sprint
C. Analyze and revise the story points of the work items completed in the previous sprint.
D. Determine which items have been finished on the previous sprint.
Correct Answer: B
Explanation/Reference:
The Sprint Retrospective is an opportunity for the Scrum Team to inspect itself and create a plan for improvements to be enacted during the next Sprint.The purpose of the Sprint Retrospective is to:· Inspect how the last Sprint went with regards to people, relationships, process, and tools;· Identify and order the major items that went well and potential improvements; and,· Create a plan for implementing improvements to the way the Scrum Team does its work.
Sprint Retrospectives are used by teams to deliberately improve. Effective Sprint Retrospectives are an important ingredient in helping good teams become great and great teams sustain themselves.
Reference : Effective Sprint Retrospectives
http://msdn.microsoft.com/en-us/library/jj620912.aspx