What should you do?

Your organization uses Microsoft Project 2013.
You are finalizing the Project Schedule for a very complex project with over 100 resources.
You need to ensure that all tasks are assigned to resources.
What should you do?
A. Use Task Usage view and look for Unassigned tasks.
B. Use Resource Graph view and look for the Unassigned resource name.
C. Use Resource Usage view and look for the Unassigned resource name.
D. Use Resource Sheet view and look for Unassigned tasks.

microsoft-exams

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.