You are a project manager who uses Project Standard 2013.
You have been told to build multiple project files for a program.
You need to have all of your projects start with auto scheduled tasks by default.
What should you do?
A. Under schedule options, set New tasks created to Auto Scheduled for each project.
B. Use the Task Mode field to change the first task to Auto Schedule, then copy down for all of your tasks.
C. Under schedule options, set New tasks created to Auto Scheduled for all new projects.
D. Highlight all of the tasks in your schedule and select the Auto Schedule button.