What should you do?

You manage a project by using Project Professional 2013.
A critical task is out of scope for the project. The stakeholders suggest that the task be removed from the project but kept in the plan in case the task is needed in the future.
You need to implement a solution to meet the stakeholder’s request.
What should you do?
A. Click on the task, and click Inactivate.
B. Move the task to after the ending date for the project.
C. Delete the task from the schedule.
D. Click the Unlink Task button to unlink the predecessors and successors for the task.