What should you do?

You use Project Professional 2013 to manage a project schedule which includes all task relationships.
The resource who is assigned to the “Develop software delivery” task is no longer available to work on your project. You can find another resource to perform this task, but you are not sure when the resource will become available.
You need to know which future tasks could be affected as a result of the resource leaving your project.
What should you do?
A. Sort all tasks by start date and check start dates of tasks that are scheduled after the Develop Software Delivery task.
B. View the critical path for tasks that are successors to the Develop Software Delivery task.
C. View the Network diagram and filter for the predecessor tasks to Develop Software Delivery task.
D. Use the Task path function to check driven successors for the Develop Software Delivery task.