What should you do?

You are a project manager who uses Project Professional 2013.
You work in a software development project, which is in progress and has reached 60% of actual progress. Your company decides to use the new Project Reports views to communicate all the project progress across the key users. They also decide to report information about a specific period only, normally one month behind the current day.
You need to access the report view that your company previously created; however, you must only modify the period displayed in the report and ensure that another period will not be presented.
What should you do?
A. Access your report and change the scale by zooming in and out.
B. Access your report and create a new Date Range group.
C. Access your report and use the default Date Range filter.
D. Access your report view and edit the time category under the field list pane.