What should you do?

You are a Project Manager who uses Project Professional 2013.
You manage a critical project, which is synchronized with a Microsoft SharePoint Task List.
One of your team members has changed a task priority to High in SharePoint, and you do not see the changed data in Project Professional 2013.
What should you do?
A. Use the Organizer to copy the Priority field from the SharePoint Task List.
B. Map the Priority field from SharePoint to Project by using File, Info.
C. Map the Priority field from SharePoint to Project by using Project, Custom Fields, Import Field.
D. Use the Task Information box to copy the Priority field from the SharePoint Task List.