What should you do?

You are a project manager who uses Project Professional 2013.
Your organization has been working with a new status report model for the last month. This new status report is created through the Built-in Dashboards and Reports in Project Professional 2013.
The standard Project Professional 2013 report views named Late Tasks and Milestone Report already have all the information required for the new model.
You are assigned to consolidate the information from these two reports into a dashboard view named Status Report Model. Your organization wants to keep the same format, colors, and layout.
You need to implement this solution.
What should you do?
A. Use the Organizer to merge the reports.
B. Select all components on each view, and copy and paste directly to a new dashboard report.
C. Use the Burndown dashboard report to view this information.
D. Use the Work Overview dashboard to view the data.