What should you do?

You are a project manager who uses Project Professional 2013.
You are planning an office move, which will occur over a weekend. You use Auto Scheduled tasks and create a weekend working calendar.
You need to assign the weekend working calendar to the task.
What should you do?
A. Change the start date of the task to the Saturday, which will assign the weekend working calendar to the task.
B. Click on the Task tab and select the Change Working Time button. Assign the weekend working calendar to the task.
C. Assign the task calendar to the task using the Task Information dialog box.
D. Right-click on the weekend on the Gantt chart and select the weekend working calendar.

microsoft-exams

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.