What should you do?

You are a project manager who uses Project Standard 2013.
A colleague sends you a Microsoft Excel file that contains a list of tasks that define a project you must complete.
You need to create a project file that contains this task list, ensuring that any fields are mapped correctly.
What should you do?
A. Add the Import Project Wizard to the Quick Access Toolbar. Initiate the wizard and select the Excel file to import.
B. Open the file in Excel, and copy and paste the tasks into a new project.
C. Rename the Excel file to tasks.mpp and open the plan in Project Standard 2013.
D. Open the Excel file by using Project Standard 2013 and import the task list using the Project Import Wizard.

microsoft-exams

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.