What should you do?

You manage a project schedule by using Project Professional 2013.
You are concerned about project costs. After viewing the Cost Variance column, you realize that the project has a cost variance of 55,000.00.
You need to view graphically which tasks and resources are causing the $5,000.00 cost variance.
What should you do?
A. View the Resource Graph’s Cumulative Cost view.
B. View the Task Cost Overview report.
C. View the Over Budget Tasks report.
D. View the Cost Overrun report.