You use Project Professional 2013 to manage a project for your organization.
You are tracking work in a project which contains a baseline and resource assignments. You want to view the work variance for a specific resource for a specific task.
You need to choose a view that will show this information.
What should you do?
A. View the Resource Sheet that shows the Work table.
B. View the Gantt chart in split view with Task form formatted to show Work Details.
C. View the Resource Sheet view and insert the Work Variance field.
D. View the Task Usage view and insert the Work Variance column on the left side of the view.