What should you do?

Your organization uses Project Online for project portfolio selection. The business drivers and priorities are set, as are the main constraints to identify the efficient frontier. The company has been collecting business cases for new proposals in which many projects may solve the same business need. For example, the selection for a Customer Relationship Management system has six different proposals, whereas only one is necessary to fulfill the business need. You need to guarantee that the analysis will produce the most viable proposal in terms of cost and resources and that no repetitive efforts exist in the portfolio selection. What should you do?
A. Create a mutual exclusion dependency among all these projects
B. Create a mutual inclusion dependency among all these projects
C. Exclude these projects from the Portfolio Analysis to prevent a deviation from the main goal
D. Exclude the related projects from the portfolio after the cost analysis with the Force in/out option.

microsoft-exams

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.