You are a project manager for an organization that uses Project Server 2013. After performing a review of all the risks created by your project team for one of your projects, you realize that the risks are not linked to their related tasks. You need to link the risks to their related tasks. What should you do?
A. Open each risk, select the Attach file option, and then select the name of the related task.
B. Open your project in Project Web App (PWA). Highlight each task and use the Related Item option for linking one or more risks for each task.
C. Create a new field for the Risk content type in SharePoint and name it "task name". Then open each risk and write the name of the related task into the new field.
D. Open each risk and copy and paste its name into the Notes field in the task page.