What should you do?

You are a project manager who uses Project Server 2013 and Project Professional 2013. You build your project plan. In the least amount of time, you need to assign resources to your plan based on their availability. What should you do?
A. Open your project in the Project Web App (PWA) and use the Resource Center Availability view to see what the availability is for each resource you would like to use. Then return to the task view and add the resources.
B. Open your project in Project Professional 2013 and add resources to your plan. Then use the Team Planner view to determine their availability.
C. Open your project in Project Professional 2013 and use the Build Team From Enterprise dialog box and filter by resource availability by time period. Then add the resources to your plan.
D. Open your project in the Project Web App (PWA) and use the Resource Center Assignments view to see where your resources are currently available before deciding which resources to use. Then add the resources to your plan.