What should you do?

You are a project manager for an organization that uses Project Server 2013. You have many projects that you schedule and manage. Your organization hires an individual that will be a resource on one of your schedules. You need to use Project Web App (PWA) to add the resource to your schedule as a Team Member so that you can assign them tasks. What should you do?
A. Edit the Project schedule and type in the name of the Resource on a task.
B. Edit the Project schedule and add the new resource in Resource Plan.
C. Edit the Project schedule and add a new task with the name of the Resource on the new task.
D. Edit the Project schedule and add the new resource in Build Team.