What should you do?

You are a project manager who uses Project Online. Your project is scheduled to run for at least 18 months. You create a schedule for the first six months, including estimated resource demand, using Project Professional 2013. For planning purposes, you need to reserve proposed demand for the final 12 months. What should you do?
A. Create new tasks in the project to represent the unplanned portion of the project. Assign resources to these tasks and set their booking type to committed.
B. Create a resource plan and enter the resource requirements for the final 12 months.
C. Create a resource plan and set the Resource Utilization to calculate from the project until a date six months from now.
D. Create new tasks in the project to represent the unplanned portion of the project. Assign resources to these tasks and set their booking type to proposed.