You are a project manager who uses Project Online. You build and publish a resource plan for your project. You check the resource demand in the Resource Availability screen. You do not see the correct demand as defined in the resource plan. You need to see the correct demand. What should you do?
A. Ensure that the date range of the resource plan matches the date range of the project plan.
B. Ensure that the resource utilization is calculated from the resource plan.
C. Ensure that the resource’s default Booking Type is set to Committed.
D. Ensure that Work Units is set to hours for the resource plan.