What should you do?

You are a resource manager and manage a project with Project Server 2013 and Project Professional 2013. Without notice, one of your key resources decides to take a leave of absence for 30 days. You need to account for the absent resource and assess how the absence will affect your schedule. What should you do?
A. Open Project Professional 2013 and manually reschedule the tasks associated with constraint dates which start when the resource returns.
B. Open the resource from the Resource Center view and edit the resource in Project Professional 2013. Then go to the Project tab and change working time and log nonworking exceptions to the availability.
C. Open the Project Web App (PWA), go to the Resource Center, and change the earliest available date to when the resource will return.
D. Open your project file in Project Professional 2013 and adjust the units for your resource to 0% available while the resource is gone.