What should you do?

You are a project manager in an organization that uses Project Online. Project managers have access to Project Professional 2013 for schedule management. You create a project schedule with resource assignments on Monday. No resources are overallocated. However, on Tuesday, you open the same project schedule and discover on several of your tasks that resources show as overallocated. Your project has a lower priority than other projects in the organization. You need to solve the overallocation by adjusting the Scheduled Start for the resources on your tasks to when the resources are available. What should you do?
A. Use Task Inspector to reschedule the tasks.
B. Use the Resource Usage view to go to next overallocation.
C. Use Team Planner view to reassign the tasks.
D. Use Task Information to change the priority number of the tasks.

microsoft-exams

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.