What should you do?

You are a project manager in an organization that uses Project Server 2013. Single entry mode is disabled. The Only allow task updates via Tasks and Timesheets option is enabled. Project team members submit updates to tasks through Project Web App (PWA).A team member submits a status update to you for approval. The team member later informs you that they made a typing mistake in the status update. You need to correct the status update. What should you do?
A. Instruct the team member to enter the correct information and send the status again.
B. Accept the status update in Project Professional 2013 and correct the user’s mistake.
C. Reject the status update in Project Professional 2013 and have the user send the correct status.
D. Instruct the team member to recall the timesheet.