Home » Microsoft » MB6-703 » What should you do?
You plan to purchase 2,400 units of one item. Two hundred units of the item will be received every month for 12 months.
You need to configure the purchase order for the item.
What should you do?
A. Configure prepayments.
B. Set the Purchase type to Journal.
C. Create a new delivery term.
D. Configure a delivery schedule.
Correct Answer: D
Explanation/Reference:
About delivery schedules [AX 2012]
* Use the delivery schedule functionality when you want to split a sales order, purchase order, or sales quotation order line into several order lines. Each order line is called a delivery line. Two or more delivery lines make up one delivery schedule. The delivery lines can vary in delivery dates, quantities, mode of delivery, and storage dimensions such as site and warehouse.
* Example of a deliver schedule for an order of 600 chairs
Total order (original order line), 600 chairs
Requested delivery schedule, 100 chairs per month
Requested delivery timeframe, 6 months, on the first of each month