What should you do?

You are using Microsoft Test Manager (MTM). You are using the Microsoft Solution Framework (MSF) for Agile Software Development process template. SharePoint integration and reporting are enabled.
You want to assess your team’s testing effort.
To do this, you need to:
• Identify how much testing has the team completed,
• Determine whether the team is likely to finish the testing on time,
• Identify how many tests have passed, failed, or blocked, and Identify how many tests are left to be run.
What should you do?
A. From the team portal, open the Test Activity Excel Report.
B. From the team portal, open the Test Plan Progress Report.
C. From the team portal, open the Test Case Readiness Excel Report.
D. Open the Test Results view in MTM.