Home » Microsoft » 70-497 » What should you do?
You are using Microsoft Test Manager (MTM).
You have a shared steps work item that you want to hide in the Shared Steps Manager.
You need to ensure that only active shared steps work items are displayed.
What should you do?
A. Change the state of the shared steps work item to Closed, then customize the filter of the Shared Steps Manager view to display shared steps that have the status Active.
B. Delete the shared steps work item from all test cases where it is used, then delete the shared steps work item from the Shared Steps Manager.
C. For the shared steps work item, change the Show in Shared Step Manager setting to Do Not Show.
D. Change the state of the shared steps work item to Removed.
Correct Answer: A
Explanation/Reference:
* To change the state of shared steps to closed
From the Testing Center, choose Organize and then choose Shared Steps Manager.
The Contents pane is displayed.
To open the shared steps to change the state, double-click the shared steps that are listed in the Shared Steps manager pane.
Choose State and then choose Closed.
* To hide the closed shared steps, you can add the state column and filter by state.
1. Right-click in the columns header of the shared steps manager.
A drop-down list of fields is displayed.
2. To select the state field, choose State from the list of fields. Choose outside the drop-down list to close it and to add the field to the columns.
3. To add a filter to the column to hide the closed shared steps, choose the drop-down arrow in the column header. Select Active to show only the active shared steps.
Reference: How to: Change the State of Shared Steps to Closed