You are using Microsoft Test Manager (MTM) to manage your testing efforts.
You want to see which work items have changed since the last time you assigned a build to the test plan.
You need to assign a new build to the test plan and create a list of the bugs that have been fixed and the features that have been associated with the new build.
What should you do? (To answer, move the three appropriate actions from the list of actions to the answer area and arrange them in the correct order.)
Select and Place:
Correct Answer:
Explanation/Reference:
Note:
* To determine changes between builds and use a new build for testing
Open Microsoft Test Manager.
To check changes between builds, choose the down-arrow on the center group selector and then choose Testing Center.
In the center group menu bar, choose Track.
Choose Assign Build.
The Assign Build activity is displayed and the available builds are shown based on your build filter.
(Optional) To display the work items for a different build, click Available builds and select a different build.
The work items are displayed in Associated items.
To use a new build for your testing for this test plan, choose Available builds and select a build and then choose Assign to plan.
* After you select the build for your test plan that you are currently using, you can select a different build to see which work items have been associated with any builds between the test plan build and this selected build. Microsoft Test Manager displays the work items that have been associated with changesets checked in between any two builds, as shown in the following illustration. You can sort these work items by associated build or by the state of the work item.