Home » Cisco » 350-080 » What will occur next?
When an NP port becomes operational, the NP switch first logs itself into the core switch by sending a FLOGI request (using the port WWN of the NP port). What will occur next?
A. The switch registers with the fabric name server.
B. The switch will perform a PLOGI to the port login server.
C. The switch will register parameters using FDISC.
D. The NPV switch will perform a PLOGI using FDISC to register with the fabric name server.
Correct Answer: A
Explanation/Reference:
Explanation:
After completing the FLOGI request, the switch registers itself with the fabric name server on the core switch (using the symbolic port name of the NP port and the IP address of the edge switch).
Reference: http://www.cisco.com/c/en/us/td/docs/switches/datacenter/nexus5500/sw/san_switching/6x/b_5500_SAN_Switching_Config_6x/b_5500_SAN_Switching_Config_602N12_chapter_0100.html#con_1482494