When is a Sprint over?
A. When the Product Owner says it is done.
B. When all Product Backlog items meet their definition of "Done".
C. When all the tasks are completed.
D. When the time-box expires.
When is a Sprint over?
A. When the Product Owner says it is done.
B. When all Product Backlog items meet their definition of "Done".
C. When all the tasks are completed.
D. When the time-box expires.
E. When the Sprint Retrospective is complete.
According the SCRUM Open assessment
D. When the time-box expires