Which element should you use?

Your organization is performing a Portfolio Analysis in Project Server 2013. You want to create a consolidated Portfolio Analysis optimization based on Cost and Resource data, which will be part of the project information in Project Server 2013. You plan to provide different simulations to your organization by using those parameters and returning the best prioritization. This organization has two different unit directors, who have the final decision on the consolidated Portfolio Analysis results.
You need to provide the ability for your unit directors to modify the final portfolio selection. Which element should you use?
A. Resource Requirements
B. Project/Proposal Priority
C. Field Cost Constraint
D. Project Original Start
E. Field Force In/Out