Which four actions should you perform in sequence?

You work as a team member for an organization that uses Project Server 2013. The organization tracks work in hours and has single-entry mode enabled. You are required to complete a timesheet at the end of each week. For this week’s timesheet, you only have one assigned task to complete. You need to ensure that your timesheet is accurate and ready for approval. Which four actions should you perform in sequence?
To answer, move the appropriate four actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place: