You manage an application hosted on cloud services. The development team creates a new version of the application. The updated application has been packaged and stored in an Azure Storage account.
You have the following requirements:
Deploy the latest version of the application to production with the least amount of downtime.
Ensure that the updated application can be tested prior to deploying to the Production site.
Ensure that the original version of the application can be restored until the new version is verified.
Which four steps should you perform in sequence? To answer, move the appropriate actions from
the list of actions to the answer area and arrange them in the correct order.
Select and Place:
Correct Answer:
Explanation/Reference:
* Cloud Services provides more control and improved access to service instances than the Azure Web Sites feature, with a cost for each role approximately the same as when using Web Sites Reserved mode. Applications can be staged for final testing before release.
* Azure Cloud Services provides both a staging and a production area for roles you deploy; you can deploy an application to either a staging or a production environment within the same Cloud Service. A common scenario is to deploy first to the staging environment and then, at the appropriate time, move the new version to the production environment. The only difference is in the URL you use to access them.
* The operations staff can deploy a new version of the application to the staging deployment slot, perform some final tests, and then swap the production and staging slots to make the new version of the application available to users.
Reference: Moving to Microsoft Azure Cloud Services
URL: http://msdn.microsoft.com/en-us/library/ff803371.aspx