Management has requested that services be available within 72 hours of a disaster. Budget is a major concern. A contract is signed with a company that has plenty of space, and the technician will have the option of putting infrastructure equipment in place. Which of the following BEST describes this business continuity strategy?
A. Cold site
B. Differential backup
C. Hot site
D. Incremental backup
E. Warm site
F. Full backup
Exam N10-008: CompTIA Network+Free dumps for N10-008 in PDF format.High quality N10-008 PDF and software. VALID exam to help you pass. |
As the name suggests, a warm site is in between a hot site and a cold site. A hot site is fully functional and allows immediate recovery from a disaster while a cold site only includes infrastructure but no technology until a disaster hits.
reference: https://searchdisasterrecovery.techtarget.com/definition/warm-site#:~:text=As%20the%20name%20suggests%2C%20a,technology%20until%20a%20disaster%20hits.