Which of the following documents should the project manager review?

A project manager is working with system owners to develop maintenance windows for system pathing and upgrades in a cloud-based PaaS environment.
Management has indicated one maintenance windows will be authorized per month, but clients have stated they require quarterly maintenance windows to meet their obligations. Which of the following documents should the project manager review?
A. MOU
B. SOW
C. SRTM
D. SLA